Town of Gravelbourg-Landfill Decommissioning
Federal contribution
$495,328
Federal share40%
of $1.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedOct 6, 2022
2023202420252026
BuiltForecast
Approved 8 weeks before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Gravelbourg
- Construction start
- Nov 20, 2023(actual)
- Construction end
- Mar 31, 2026(forecast)
Also in Gravelbourg
- Town of Gravelbourg Water Tower Decommissioning and Watermain Replacement$1.4M
- Gravelbourg Water Treatment Plant Upgrades - Phase 2$1.0M
- Town of Gravelbourg-Water Treatment Plant Upgrade$250.0K
- Bridge Replacement in Gravelbourg$150.0K
- Purchase of a hybrid vehicle and construction of a garage for on-demand service in Gravelbourg and rural southwest Saskatchewan$78.9K