Resurfacing Highway 169 between Val-Jalbert and Chambord - Phase 1
Federal contribution
$685,320
Federal share41%
of $1.7M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedSep 13, 2009
ApprovedJan 26, 2010
20102011
Built
Approved 4 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Quebec
- Construction start
- Aug 26, 2010(actual)
- Construction end
- Sep 9, 2011(actual)
Against the original forecast
- Construction start2 months lateforecast Jun 15, 2010
- Construction end6 weeks lateforecast Jul 31, 2011
Also in Chambord
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 35943 in the federal list. How to read these figures.