Resurfacing Highway 169 between Val-Jalbert and Chambord - Phase 1

Chambord, Quebec

completeHighways and RoadsISF
Federal contribution
$685,320
Federal share41%

of $1.7M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedSep 13, 2009
ApprovedJan 26, 2010
20102011
Built

Approved 4 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Quebec
Construction start
Aug 26, 2010(actual)
Construction end
Sep 9, 2011(actual)

Against the original forecast

  • Construction start2 months lateforecast Jun 15, 2010
  • Construction end6 weeks lateforecast Jul 31, 2011

Also in Chambord

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 35943 in the federal list. How to read these figures.