Back to projects

Resurfacing of Highway 167

Chambord, Quebec

completeHighways and RoadsISF
Federal contribution
$661,000
Federal share50%

of $1.3M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedSep 13, 2009
ApprovedJan 26, 2010
20102011
Built

Approved 4 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Quebec
Construction start
Aug 21, 2011(actual)
Construction end
Sep 15, 2011(actual)

Against the original forecast

  • Construction start3 weeks lateforecast Aug 1, 2011
  • Construction end7 weeks earlyforecast Oct 31, 2011