Resurfacing of Highway 167
Federal contribution
$661,000
Federal share50%
of $1.3M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedSep 13, 2009
ApprovedJan 26, 2010
20102011
Built
Approved 4 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Quebec
- Construction start
- Aug 21, 2011(actual)
- Construction end
- Sep 15, 2011(actual)
Against the original forecast
- Construction start3 weeks lateforecast Aug 1, 2011
- Construction end7 weeks earlyforecast Oct 31, 2011
Also in Chambord