Improvements to Highway 40 westbound in the Municipality of Louiseville

Louiseville, Quebec

completeHighways and RoadsISF
Federal contribution
$441,690
Federal share32%

of $1.4M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedSep 13, 2009
ApprovedJan 26, 2010
2010
Built

Approved 4 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Quebec
Construction start
Aug 12, 2010(actual)
Construction end
Aug 27, 2010(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Jul 15, 2010
  • Construction end2 months earlyforecast Oct 31, 2010