Water System Upgrades

Louiseville, Quebec

completeWastewaterGIS
Federal contribution
$698,548
Federal share40%

of $1.7M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 12, 2020
202120222023
Built

Approved 6 weeks before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
City of Louiseville
Construction start
Oct 12, 2021(actual)
Construction end
Sep 30, 2023(actual)

Against the original forecast

  • Construction start5 months lateforecast May 27, 2021
  • Construction end3 months lateforecast Jun 29, 2023