Asphalt Paving
Federal contribution
$330,205
Federal share17%
of $2.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 11, 2009
2010
Built
Approved 2 weeks after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Toronto
- Construction start
- Jul 15, 2010(actual)
- Construction end
- Oct 8, 2010(actual)
Against the original forecast
- Construction start4 weeks lateforecast Jun 15, 2010
- Construction end3 months earlyforecast Dec 31, 2010
Also in Toronto