Toronto Police Station Asphalt Repavement - 41 Division
Federal contribution
$105,704
Federal share20%
of $535.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 11, 2009
2010
Built
Approved 2 weeks after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Toronto
- Construction start
- May 17, 2010(actual)
- Construction end
- Aug 30, 2010(actual)
Against the original forecast
- Construction start2 weeks lateforecast May 1, 2010
- Construction end4 months earlyforecast Dec 31, 2010
Also in Toronto