Deep Lake Water Cooling System - Front Street
Federal contribution
$588,333
Federal share33%
of $1.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 11, 2009
20102011
Built
Approved 2 weeks after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Toronto
- Construction start
- Jul 6, 2010(actual)
- Construction end
- Oct 31, 2011(actual)
Against the original forecast
- Construction start5 weeks lateforecast Jun 1, 2010
- Construction end12 months lateforecast Oct 31, 2010
Also in Toronto
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 35987 in the federal list. How to read these figures.