Improvements to Salt Management Facilities - Kipling Yard

Toronto, Ontario

completeHighways and RoadsISF
Federal contribution
$550,522
Federal share28%

of $2.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 11, 2009
2010
Built

Approved 2 weeks after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Toronto
Construction start
May 11, 2010(actual)
Construction end
Oct 22, 2010(actual)

Against the original forecast

  • Construction end5 months earlyforecast Mar 31, 2011

Also in Toronto

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 35990 in the federal list. How to read these figures.