Bloor-Islington Bridge Rehabilitation
Federal contribution
$344,828
Federal share33%
of $1.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 11, 2009
20102011
Built
Approved 2 weeks after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Toronto
- Construction start
- Apr 10, 2010(actual)
- Construction end
- May 31, 2011(actual)
Against the original forecast
- Construction start4 months earlyforecast Aug 19, 2010
- Construction end5 months lateforecast Dec 15, 2010