Back to projects

Reconstruction and Resurfacing of Leslie Street

Toronto, Ontario

completeHighways and RoadsISF
Federal contribution
$141,452
Federal share27%

of $533.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 11, 2009
2010
Built

Approved 2 weeks after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Toronto
Construction start
Sep 28, 2009(actual)
Construction end
Nov 15, 2010(actual)

Against the original forecast

  • Construction start8 weeks lateforecast Aug 1, 2009
  • Construction end4 months lateforecast Jul 31, 2010