Reconstruction and Resurfacing of Lawrence Avenue West
Federal contribution
$442,931
Federal share27%
of $1.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 11, 2009
2010
Built
Approved 2 weeks after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Toronto
- Construction start
- Jan 5, 2010(actual)
- Construction end
- Aug 31, 2010(actual)
Against the original forecast
- Construction start4 months earlyforecast May 1, 2010
Also in Toronto
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 36011 in the federal list. How to read these figures.