Emergency Repair of Coxwell Sanitary Sewer
Federal contribution
$9.7M
$9,662,530
Federal share24%
of $40.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 11, 2009
20102011201220132014
Built
Approved 2 weeks after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Toronto
- Construction start
- Apr 9, 2010(actual)
- Construction end
- Nov 29, 2013(actual)
Against the original forecast
- Construction start6 weeks earlyforecast May 22, 2010
- Construction end2 weeks lateforecast Nov 15, 2013
Also in Toronto
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 36016 in the federal list. How to read these figures.