Coatsworth Cut Water Quality Improvements

Toronto, Ontario

completeWastewaterISF
Federal contribution
$2.0M
$2,026,874
Federal share29%

of $7.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 11, 2009
20102011
Built

Approved 2 weeks after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Toronto
Construction start
Nov 18, 2010(actual)
Construction end
May 20, 2011(actual)

Against the original forecast

  • Construction start2 months lateforecast Sep 15, 2010
  • Construction end19 months earlyforecast Dec 31, 2012