Solid Waste Management - Yonge Yard Improvements

Toronto, Ontario

completeSolid Waste ManagementISF
Federal contribution
$298,814
Federal share30%

of $1.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 11, 2009
20102011
Built

Approved 2 weeks after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Toronto
Construction start
Oct 1, 2010(actual)
Construction end
Oct 31, 2011(actual)

Against the original forecast

  • Construction start9 months lateforecast Jan 2, 2010
  • Construction end4 weeks lateforecast Sep 30, 2011