Solid Waste Management - Yonge Yard Improvements
Federal contribution
$298,814
Federal share30%
of $1.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 11, 2009
20102011
Built
Approved 2 weeks after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Toronto
- Construction start
- Oct 1, 2010(actual)
- Construction end
- Oct 31, 2011(actual)
Against the original forecast
- Construction start9 months lateforecast Jan 2, 2010
- Construction end4 weeks lateforecast Sep 30, 2011
Also in Toronto
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 36029 in the federal list. How to read these figures.