Maryvale Park - Trails and Pathways Rehabilitation
Federal contribution
$39,900
Federal share33%
of $120.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 11, 2009
2010
Built
Approved 2 weeks after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Toronto
- Construction start
- Sep 16, 2010(actual)
- Construction end
- Oct 15, 2010(actual)
Against the original forecast
- Construction end2 weeks earlyforecast Oct 30, 2010
Also in Toronto
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 36051 in the federal list. How to read these figures.