Morningside Park - Trails and Pathways Rehabilitation

Toronto, Ontario

completeActive TransportationISF
Federal contribution
$92,103
Federal share26%

of $350.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 11, 2009
2010
Built

Approved 2 weeks after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Toronto
Construction start
Jul 5, 2010(actual)
Construction end
Nov 15, 2010(actual)

Against the original forecast

  • Construction end7 weeks lateforecast Sep 30, 2010