Back to projects

Replacement of Vintage Cast Iron Watermains

Toronto, Ontario

completeDrinking WaterISF
Federal contribution
$366,667
Federal share33%

of $1.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 11, 2009
20102011
Built

Approved 2 weeks after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Toronto
Construction start
Sep 22, 2010(actual)
Construction end
May 31, 2011(actual)

Against the original forecast

  • Construction start5 months lateforecast May 3, 2010
  • Construction end5 months lateforecast Dec 31, 2010

Also in Toronto

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 36062 in the federal list. How to read these figures.