Rouge Beach Park - Trails and Pathways Rehabilitation
Federal contribution
$28,203
Federal share9%
of $300.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 11, 2009
2010
Built
Approved 2 weeks after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Toronto
- Construction start
- Nov 8, 2010(actual)
- Construction end
- Dec 3, 2010(actual)
Against the original forecast
- Construction start5 weeks lateforecast Oct 1, 2010
- Construction end4 weeks earlyforecast Dec 30, 2010