Driftwood Park - Trails and Pathways Rehabilitation
Federal contribution
$27,172
Federal share30%
of $90.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 11, 2009
20102011
Built
Approved 2 weeks after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Toronto
- Construction start
- Oct 18, 2010(actual)
- Construction end
- Oct 31, 2011(actual)
Against the original forecast
- Construction start3 weeks lateforecast Sep 30, 2010
- Construction end2 months lateforecast Aug 30, 2011