Replacement of Vintage Cast Iron Watermains

Toronto, Ontario

completeDrinking WaterISF
Federal contribution
$866,667
Federal share33%

of $2.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 11, 2009
2010
Built

Approved 2 weeks after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Toronto
Construction start
Aug 13, 2010(actual)
Construction end
Oct 1, 2010(actual)

Against the original forecast

  • Construction start3 months lateforecast May 3, 2010
  • Construction end3 months earlyforecast Dec 31, 2010