Installation of Stormwater Management at the Green Lane Landfill

St. Thomas, Ontario

completeWastewaterISF
Federal contribution
$201,000
Federal share33%

of $603.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 11, 2009
20102011
Built

Approved 2 weeks after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Toronto
Construction start
Oct 6, 2009(actual)
Construction end
Oct 31, 2011(actual)

Against the original forecast

  • Construction start2 months lateforecast Aug 1, 2009

Also in St. Thomas