Clanton Park - Trails and Pathways Rehabilitation
Federal contribution
$37,296
Federal share32%
of $115.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 11, 2009
20102011
Built
Approved 2 weeks after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Toronto
- Construction start
- Oct 14, 2010(actual)
- Construction end
- Jan 3, 2011(actual)
Against the original forecast
- Construction start4 weeks lateforecast Sep 15, 2010
- Construction end3 weeks lateforecast Dec 10, 2010