Back to projects

Woodford Park - Trails and Pathways Rehabilitation

Toronto, Ontario

completeActive TransportationISF
Federal contribution
$17,541
Federal share32%

of $55.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 11, 2009
2010
Built

Approved 2 weeks after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Toronto
Construction start
Aug 9, 2010(actual)
Construction end
Aug 24, 2010(actual)

Against the original forecast

  • Construction start3 weeks lateforecast Jul 19, 2010
  • Construction end5 weeks earlyforecast Sep 30, 2010

Also in Toronto

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 36110 in the federal list. How to read these figures.