West Deane Park North - Trails and Pathways Repair
Federal contribution
$116,655
Federal share33%
of $350.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 11, 2009
2010
Built
Approved 2 weeks after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Toronto
- Construction start
- Aug 26, 2010(actual)
- Construction end
- Oct 4, 2010(actual)
Against the original forecast
- Construction start2 weeks lateforecast Aug 9, 2010
- Construction end4 weeks earlyforecast Oct 31, 2010
Also in Toronto
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 36114 in the federal list. How to read these figures.