Two New Covered Bunkers for Bermondsey Transfer Station

Toronto, Ontario

completeSolid Waste ManagementISF
Federal contribution
$463,476
Federal share32%

of $1.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 11, 2009
20102011
Built

Approved 2 weeks after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Toronto
Construction start
Jul 28, 2010(actual)
Construction end
Oct 1, 2011(actual)

Against the original forecast

  • Construction start4 months lateforecast Apr 1, 2010
  • Construction end2 months lateforecast Jul 28, 2011