New Central Lockup for the 11th Division of the Toronto Police
Federal contribution
$9.4M
$9,440,828
Federal share32%
of $29.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 11, 2009
20102011
Built
Approved 2 weeks after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Toronto
- Construction start
- Oct 26, 2009(actual)
- Construction end
- Jul 22, 2011(actual)
Against the original forecast
- Construction start8 weeks lateforecast Sep 1, 2009
- Construction end7 weeks lateforecast May 31, 2011