Regent Park Arts and Cultural Centre

Toronto, Ontario

completeCultureISF
Federal contribution
$9.4M
$9,386,812
Federal share39%

of $24.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 16, 2009
201020112012
Built

Approved 3 weeks after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Toronto
Construction start
May 3, 2010(actual)
Construction end
Sep 25, 2012(actual)

Against the original forecast

  • Construction start8 weeks earlyforecast Jun 30, 2010
  • Construction end5 weeks earlyforecast Oct 31, 2012

Also in Toronto

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 36148 in the federal list. How to read these figures.