Agincourt Library Renovation

Toronto, Ontario

completeCultureISF
Federal contribution
$270,000
Federal share33%

of $810.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 11, 2009
2010
Built

Approved 2 weeks after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Toronto
Construction start
Dec 1, 2009(actual)
Construction end
Dec 6, 2010(actual)

Against the original forecast

  • Construction start2 months lateforecast Oct 1, 2009
  • Construction end4 months earlyforecast Mar 31, 2011

Also in Toronto

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 36152 in the federal list. How to read these figures.