Richview Library

Toronto, Ontario

completeCultureISF
Federal contribution
$166,667
Federal share33%

of $500.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 11, 2009
20102011
Built

Approved 2 weeks after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Toronto
Construction start
Apr 19, 2010(actual)
Construction end
Dec 31, 2010(actual)

Against the original forecast

  • Construction start4 months earlyforecast Aug 30, 2010
  • Construction end3 months earlyforecast Mar 31, 2011

Also in Toronto

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 36155 in the federal list. How to read these figures.