Back to projects

Lead Water Service Pipe Replacement

Toronto, Ontario

completeDrinking WaterISF
Federal contribution
$13,020
Federal share21%

of $62.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 11, 2009
20102011
Built

Approved 2 weeks after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Toronto
Construction start
May 31, 2010(actual)
Construction end
Dec 17, 2010(actual)

Against the original forecast

  • Construction start3 months lateforecast Mar 1, 2010
  • Construction end3 months earlyforecast Mar 31, 2011

Also in Toronto

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 36159 in the federal list. How to read these figures.