Lead Water Service Pipe Replacement
Federal contribution
$38,540
Federal share21%
of $185.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 11, 2009
20102011
Built
Approved 2 weeks after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Toronto
- Construction start
- Jul 9, 2010(actual)
- Construction end
- Feb 25, 2011(actual)
Against the original forecast
- Construction start7 weeks lateforecast May 21, 2010
- Construction end5 months lateforecast Oct 9, 2010
Also in Toronto
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 36161 in the federal list. How to read these figures.