Lead Water Service Pipe Replacement
Federal contribution
$16,666
Federal share21%
of $80.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 11, 2009
20102011
Built
Approved 2 weeks after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Toronto
- Construction start
- May 31, 2010(actual)
- Construction end
- Dec 17, 2010(actual)
Against the original forecast
- Construction start4 weeks lateforecast Apr 30, 2010
- Construction end3 months lateforecast Sep 18, 2010