Lead Water Service Pipe Replacement

Toronto, Ontario

completeDrinking WaterISF
Federal contribution
$28,124
Federal share21%

of $135.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 11, 2009
20102011
Built

Approved 2 weeks after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Toronto
Construction start
Jul 9, 2010(actual)
Construction end
Dec 17, 2010(actual)

Against the original forecast

  • Construction start7 weeks lateforecast May 21, 2010
  • Construction end2 months lateforecast Oct 9, 2010