Lead Water Service Pipe Replacement

Toronto, Ontario

completeDrinking WaterISF
Federal contribution
$11,249
Federal share21%

of $54.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 11, 2009
20102011
Built

Approved 2 weeks after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Toronto
Construction start
Oct 14, 2010(actual)
Construction end
Jul 25, 2011(actual)

Against the original forecast

  • Construction start4 months lateforecast May 31, 2010
  • Construction end4 months lateforecast Mar 31, 2011