Back to projects

Reconstruction and Expansion of Emergency Medical Services Station 40

Toronto, Ontario

completeHealthcare InfrastructureISF
Federal contribution
$756,683
Federal share24%

of $3.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 11, 2009
20102011
Built

Approved 2 weeks after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Toronto
Construction start
Jun 17, 2010(actual)
Construction end
Mar 31, 2011(actual)

Against the original forecast

  • Construction start7 weeks lateforecast May 1, 2010

Also in Toronto