Lead Water Service Pipe Replacement
Federal contribution
$23,749
Federal share21%
of $114.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 11, 2009
2010
Built
Approved 2 weeks after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Toronto
- Construction start
- Jul 23, 2010(actual)
- Construction end
- Sep 21, 2010(actual)
Against the original forecast
- Construction start3 months lateforecast Apr 15, 2010
- Construction end6 months earlyforecast Mar 31, 2011
Also in Toronto
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 36188 in the federal list. How to read these figures.