Exhibition Place - Horse Palace Roof Replacement

Toronto, Ontario

completeTourismISF
Federal contribution
$699,817
Federal share33%

of $2.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 11, 2009
20102011
Built

Approved 2 weeks after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Toronto
Construction start
Sep 29, 2010(actual)
Construction end
Oct 31, 2011(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Sep 1, 2010

Also in Toronto