Transportation Facility Improvements

Toronto, Ontario

completeHighways and RoadsISF
Federal contribution
$270,116
Federal share22%

of $1.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 11, 2009
2010
Built

Approved 2 weeks after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Toronto
Construction start
Jan 11, 2010(actual)
Construction end
May 30, 2010(actual)

Against the original forecast

  • Construction start6 weeks lateforecast Dec 1, 2009
  • Construction end10 months earlyforecast Mar 31, 2011