Transportation Facility Improvements
Federal contribution
$270,116
Federal share22%
of $1.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 11, 2009
2010
Built
Approved 2 weeks after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Toronto
- Construction start
- Jan 11, 2010(actual)
- Construction end
- May 30, 2010(actual)
Against the original forecast
- Construction start6 weeks lateforecast Dec 1, 2009
- Construction end10 months earlyforecast Mar 31, 2011
Also in Toronto
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 36230 in the federal list. How to read these figures.