Laneway Improvements
Federal contribution
$23,633
Federal share33%
of $71.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 11, 2009
2010
Built
Approved 2 weeks after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Toronto
- Construction start
- May 10, 2010(actual)
- Construction end
- Nov 1, 2010(actual)
Against the original forecast
- Construction start6 weeks lateforecast Mar 29, 2010
- Construction end3 months lateforecast Aug 2, 2010
Also in Toronto
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 36235 in the federal list. How to read these figures.