Rehabilitation of Trails and Pathways - Birchmount Stadium Park

Toronto, Ontario

completeActive TransportationISF
Federal contribution
$47,989
Federal share30%

of $160.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 11, 2009
2010
Built

Approved 2 weeks after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Toronto
Construction start
Jul 10, 2010(actual)
Construction end
Oct 4, 2010(actual)

Against the original forecast

  • Construction start5 weeks earlyforecast Aug 16, 2010
  • Construction end6 weeks earlyforecast Nov 15, 2010