Rehabilitation of Trails and Pathways - Birchmount Stadium Park
Federal contribution
$47,989
Federal share30%
of $160.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 11, 2009
2010
Built
Approved 2 weeks after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Toronto
- Construction start
- Jul 10, 2010(actual)
- Construction end
- Oct 4, 2010(actual)
Against the original forecast
- Construction start5 weeks earlyforecast Aug 16, 2010
- Construction end6 weeks earlyforecast Nov 15, 2010