Rehabilitation of Trails and Pathways - Lavery Trail Park
Federal contribution
$3,548
Federal share9%
of $40.0K total eligible cost; the rest comes from other partners.
Approved 2 weeks after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Toronto
- Construction start
- Nov 24, 2009(actual)
- Construction end
- Nov 30, 2009(actual)
Against the original forecast
- Construction start4 months earlyforecast Apr 1, 2010
- Construction end11 months earlyforecast Nov 15, 2010
Also in Toronto
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 36246 in the federal list. How to read these figures.