Laneway Improvements

Toronto, Ontario

completeHighways and RoadsISF
Federal contribution
$45,935
Federal share33%

of $138.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 11, 2009
2010
Built

Approved 2 weeks after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Toronto
Construction start
May 10, 2010(actual)
Construction end
Nov 1, 2010(actual)

Against the original forecast

  • Construction start6 weeks lateforecast Mar 29, 2010
  • Construction end3 months lateforecast Aug 2, 2010