Lead Water Service Pipe Replacement

Toronto, Ontario

completeDrinking WaterISF
Federal contribution
$8,125
Federal share21%

of $39.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 11, 2009
20102011
Built

Approved 2 weeks after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Toronto
Construction start
Jan 24, 2011(actual)
Construction end
May 31, 2011(actual)

Against the original forecast

  • Construction start9 months lateforecast May 2, 2010
  • Construction end2 months lateforecast Mar 31, 2011