Local Road Resurfacing
Federal contribution
$18,344
Federal share27%
of $68.7K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedSep 11, 2009
ApprovedSep 25, 2009
2010
Built
Approved 2 weeks after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Toronto
- Construction start
- Sep 11, 2009(actual)
- Construction end
- Dec 31, 2009(actual)
Against the original forecast
- Construction start6 weeks lateforecast Aug 1, 2009
- Construction end12 months earlyforecast Dec 31, 2010
Also in Toronto
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 36320 in the federal list. How to read these figures.