Lead Water Service Pipe Replacement
Federal contribution
$3,125
Federal share21%
of $15.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 11, 2009
2010
Built
Approved 2 weeks after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Toronto
- Construction start
- Sep 16, 2010(actual)
- Construction end
- Nov 19, 2010(actual)
Against the original forecast
- Construction start7 months lateforecast Mar 1, 2010
- Construction end4 months earlyforecast Mar 31, 2011