Lead Water Service Pipe Replacement
Federal contribution
$15,624
Federal share21%
of $75.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 11, 2009
20102011
Built
Approved 2 weeks after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Toronto
- Construction start
- Sep 29, 2010(actual)
- Construction end
- Mar 25, 2011(actual)
Against the original forecast
- Construction start8 weeks lateforecast Aug 4, 2010
- Construction end3 months lateforecast Dec 23, 2010
Also in Toronto
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 36331 in the federal list. How to read these figures.