Local Road Resurfacing
Federal contribution
$44,600
Federal share27%
of $167.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 11, 2009
2010
Built
Approved 2 weeks after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Toronto
- Construction start
- May 3, 2010(actual)
- Construction end
- Aug 3, 2010(actual)
Against the original forecast
- Construction start5 weeks earlyforecast Jun 10, 2010
- Construction end4 weeks earlyforecast Aug 31, 2010
Also in Toronto
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 36354 in the federal list. How to read these figures.