Local Road Resurfacing
Federal contribution
$40,485
Federal share27%
of $151.6K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 11, 2009
2010
Built
Approved 2 weeks after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Toronto
- Construction start
- Jul 7, 2010(actual)
- Construction end
- Nov 26, 2010(actual)
Against the original forecast
- Construction start4 weeks lateforecast Jun 11, 2010
- Construction end4 weeks lateforecast Oct 31, 2010
Also in Toronto
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 36358 in the federal list. How to read these figures.