Local Road Reconstruction
Federal contribution
$32,351
Federal share31%
of $104.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 11, 2009
2010
Built
Approved 2 weeks after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Toronto
- Construction start
- Jul 7, 2010(actual)
- Construction end
- Nov 25, 2010(actual)
Against the original forecast
- Construction end2 weeks lateforecast Nov 8, 2010
Also in Toronto
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 36403 in the federal list. How to read these figures.